A contractor 2
A contractor has to complete his contract in 92 days. 234 men were set to do the work, each of them works for 16 hours/day. After 66 days, 4/7 of the work is completed. How many additional men may be employed, so that the work may be completed in time, each of additional men work 18h/day.
Correct answer:

Showing 1 comment:
Dr Math
contract period =92 days.
234 men work for 16 hours/day.
In 66 days they did 4/7 of the work .
addl men work 18h/day.
Work left 1-4/7=3/7
Days left 92-66=26
66 days 4/7 work
In 26 days will do 26*4/7*66=52/231
Work left = 3/7-52/231 =(99-52)/231=47/231
4/7 in 66*234*16 hours
1 work in 66*234*16*7/4 hours
47/231 work will do in 66*234*16*7/4*47/231 hours
= By 66*234*16*7/4*47/231/(26*18) men
=(66*234*16*7*47)/(4*231*26*18)= 188 men
234 men work for 16 hours/day.
In 66 days they did 4/7 of the work .
addl men work 18h/day.
Work left 1-4/7=3/7
Days left 92-66=26
66 days 4/7 work
In 26 days will do 26*4/7*66=52/231
Work left = 3/7-52/231 =(99-52)/231=47/231
4/7 in 66*234*16 hours
1 work in 66*234*16*7/4 hours
47/231 work will do in 66*234*16*7/4*47/231 hours
= By 66*234*16*7/4*47/231/(26*18) men
=(66*234*16*7*47)/(4*231*26*18)= 188 men
Tips for related online calculators
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Embankment 56451
Twenty men will build a dam in 36 days if they work 10 hours daily. How many hours a day do 30 men have to work if the embankment is to be completed in 16 days?
- Working group
20 men complete one-third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days?
- Work in factory
45 men can complete a work in 16 days, but after some days they started working 30 more men joined them and completed the remaining work in 6 days. How many days after the commencement of the job did 30 men join?
- Bricklayers
Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days?
- Common work
39 men can repair a road in 12 days working 5 hours a day. How many days will be required to complete the work by 30 men working 6 hours a day?
- Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days?
- Forestry workers
41 laborers have employed planted trees in the forest. For 7 hour work, a day would end job in 32 days. After 12 days, 7 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 8 hours a day?