Manday, manhour
Job problem: 10 men can make 20 toys in 12 days working 12 hours a day.Then, in how many days can 24 persons make 32 toys working 16 hours a day?
Correct answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Work in factory
45 men can complete a work in 16 days, but after some days they started working 30 more men joined them and completed the remaining work in 6 days. How many days after the commencement of the job did 30 men join?
- Common work
39 men can repair a road in 12 days working 5 hours a day. How many days will be required to complete the work by 30 men working 6 hours a day?
- Embankment 56451
Twenty men will build a dam in 36 days if they work 10 hours daily. How many hours a day do 30 men have to work if the embankment is to be completed in 16 days?
- Working group
20 men complete one-third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days?
- Planting 27201
In the forest, there are 84 workers employed in planting saplings. Working 10 hours a day, they would finish the job in 24 days. After 7 days, 14 workers leave. How long will it take the others to finish planting the saplings if they work 12 hours a day f
- Working together on project
Two employees did working on the project. First, make it alone for 20 days, the second for 24 days. How many days will it take to complete the project if five days they work together, then first will take two days holiday, and after returning they complet
- A contractor 2
A contractor has to complete his contract in 92 days. 234 men were set to do the work, each of them works for 16 hours/day. After 66 days, 4/7 of the work is completed. How many additional men may be employed, so that the work may be completed in time, ea