Installation 4123
The team of installers is to carry out the installation in 20 days. By adding two fitters from the beginning of the work, the assembly was completed in 15 days. How many were on the team?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Workhorses
A team of colleagues did the work in 20 days. After adding two colleagues from the beginning, the team completed the work in 15 days. How many members has the colleague team? - Installed 5793
A group of fitters installed the cable line in 9 changes, and the second group completed the same task in 1/3 less time. How many shifts would the third group do the same work if, with all three groups working together, the assembly took 2 shifts? - Construction 1639
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Painters
The first team of painters would paint the bridge in 15 days, the second in 10 days. After three days of working together, the second team goes out and continues only with the first team. How many days took the second team to finish painting the bridge?
- Toothpaste 27001
The father would use the toothpaste alone for 15 days, the mother for 12 days, and the daughter for ten days. It was used by all three for three days, then only the father and mother. How many days have they used it since the beginning of its use? - Double-performance 17931
Excavation work was carried out by nine double-performance machines, which excavated 420 meters of excavation in one day. How many were there if the more powerful machine excavated 420 meters in a week (7 days) and the less powerful engine excavated 280 m - Performance 31371
According to the plan, seven pavers were to pave the square in 14 days. After two days of work, another 5 pavers came to help them. How many days from the arrival of the pavers will the work be completed? (tile performance is the same)