Construction 7709
Two construction companies are working on the landscaping. The first would do the whole job in 12 days, the second in 20 days. How long will they work together if the first start working when the second has already worked 4 days?
Correct answer:

Tips for related online calculators
Looking for calculator of harmonic mean?
Looking for a statistical calculator?
Need help calculating sum, simplifying, or multiplying fractions? Try our fraction calculator.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Looking for a statistical calculator?
Need help calculating sum, simplifying, or multiplying fractions? Try our fraction calculator.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Workers
Two workers would fulfill a certain task when working together for 10 days, the first if he worked himself done work in 17 days. How many days will the second worker do the whole job?
- Two companies
The family ordered two companies to modify the garden. The first would be done in 20 days; the second would take 40% less time. How long will they work together if the second company started working when the first worked for four days?
- Together 81046
Two painters are painting the factory fence together. If everyone worked alone, the first would finish the job in 16 days, the second in 20 days. When will they finish the work together?
- Together 39671
Three workers were to lay the parquet floor. If everyone worked alone, the first would finish the job in 30 hours, the second in 24 hours, and the third in 20 hours. How long will they do the floor if they work together?
- Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c
- Engineering 54971
Two engineering companies have the same production program. The first company would fulfill their orders in 20 days. The second company in 16 days. How long will the companies fulfill the order if the first company starts working 2 days earlier?
- Boots
Master shoemaker has three apprentices. First, do one pair of boots for two days, second for one day, and third for 1.5 days. How long would it take to make a couple of boots if they worked together?