Part-timers 6436
Five part-timers ship all goods from the warehouse in 12 days. Calculate how long it would take to bring twice as many goods out of the warehouse to part-timers if their number increased by 140%.
Correct answer:

Tips for related online calculators
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Part-timers 6344
Certain work was to be done by 21 workers during an eight-hour workday, due in 12 days. After five days, temporary workers came to their aid. They all worked together for 7 hours a day and finished the job in 6 days. How many part-timers were there?
- Opportunities 8372
There are 20 students in the class, four of them are being tested by the teacher. How many options are there to choose who the teacher will test?
- Part-timers
Six part-timers would take seven hours to pick strawberries. How long would this work take if two more temporary workers were added after three hours?
- Performance
Two masons with the same performance would have been made of plaster for six days. One of them, however, has increased its daily performance by 50%. How long would it take them now to make plaster together?
- The work
The work was to be done by 150 workers. At the beginning of their work, The company reduced their number by 40, which increased the work time by 5 and 1/3 of the schedule. How long did the work take?
- Two workers
Two workers should fulfill specific tasks together for five days. If the first worker increased their performance twice and the second twice fell, it took them just four days. For how many days would he handle the entire task, the first worker himself?
- Wheat plus and minus
If the price of wheat is increased by 20% today, at what percent should it be decreased tomorrow, so as to bring down the price back to the original?