Fulfillment 5210
This company can complete the order in 168 days. The second company is better equipped and can fulfill the order in 120 days. The companies will fulfill the orders together. Determine how long it will take them to fulfill the order and in what proportion they will participate in its fulfillment.
Correct answer:
Tips for related online calculators
Need help calculating sum, simplifying, or multiplying fractions? Try our fraction calculator.
Check out our ratio calculator.
Do you want to convert time units like minutes to seconds?
Check out our ratio calculator.
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Engineering 54971
Two engineering companies have the same production program. The first company would fulfill their orders in 20 days. The second company in 16 days. How long will the companies fulfill the order if the first company starts working 2 days earlier? - Two companies
Company A can fulfill the order in 12 days, and company B can fulfill the same order in 18 days. If only company A works on the order for the first two days and then both companies work on it for the remaining days, how many days will the order be fulfill - Two companies
The family ordered two companies to modify the garden. The first would be done in 20 days; the second would take 40% less time. How long will they work together if the second company started working when the first worked for four days? - Two companies
The two companies did work together for 100 days. The first company would do it in 150 days. How many days would the work take the second company?
- Technicians 8382
The order required six technicians to complete it in 18 days. How long will it take for one, two, three, four, five, six, eight, ten, and twenty technicians to complete it? - Digging companies
Company A would dig a pit for 12 days, company B for 15 days, company C for 20 days, and company D for 24 days. Work began with companies C and D, but after three days, They joined the other two companies. How long did it take to dig a pit? - Working together on project
Two employees did working on the project. First, make it alone for 20 days, the second for 24 days. How many days will it take to complete the project if five days they work together, then first will take two days holiday, and after returning they complet