Diggers
Eight diggers will do the job in 85 hours. After 21 hours, three diggers had to leave. How many hours will the work be done?
Correct answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Seamstresses 82403
Eight seamstresses sew an order in 85 hours. After 21 hours, 3 seamstresses had to leave for other work. In how many more hours will the order be fulfilled? How many hours did the whole job take?
- Contract
Eight employees complete the contract for 65 hours. After 17 hours, three employees had to leave for another job. How many more hours will the job on the contract be fulfilled?
- Planting 27201
In the forest, there are 84 workers employed in planting saplings. Working 10 hours a day, they would finish the job in 24 days. After 7 days, 14 workers leave. How long will it take the others to finish planting the saplings if they work 12 hours a day f
- Part-timers 6344
Certain work was to be done by 21 workers during an eight-hour workday, due in 12 days. After five days, temporary workers came to their aid. They all worked together for 7 hours a day and finished the job in 6 days. How many part-timers were there?
- Two workers
Two workers work together and perform the job in 12 hours. If one has done half the work and then the second worker does the next half of the work, it will take 25 hours. How long would it take to job them separately?
- Workers
Two workers would fulfill a certain task when working together for 10 days, the first if he worked himself done work in 17 days. How many days will the second worker do the whole job?
- Work together
Two bricklayers are plastering a wall. The first would plaster it in 8 hours, the second in 12 hours. If they work together, how many hours will they be done?