If x men can complete a work in 8 days and x+4 men can complete the same work in 6 days. Find the value of x.
Correct answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
You need to know the following knowledge to solve this word math problem:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Two men
2 men or 3 women can do a piece of work in 45 days. Find, in how many days 6 men and 1 women be able to complete the same work.
- 7 men
Seven men can complete work in 52 days. How many days will 13 men finish the same work?
- Three men
If three men can do a job in 8 days, how many men can do the same job in 6 days?
- Worker 25
Worker A can do 2/3 of a certain work in 12 days and B can do 1/6 of the same work in 4 days, Find in how many days will they together complete the work?
- Men at work
8 men can finish a piece of work in 40 days. If 2 more men joined with them, then how many days it will take to complete the work?
- Common work
39 men can repair a road in 12 days working 5 hours a day. How many days will be required to complete the work by 30 men working 6 hours a day?
- Work in factory
45 men can complete a work in 16 days, but after some days they started working 30 more men joined them and completed the remaining work in 6 days. How many days after the commencement of the job did 30 men join?