Bricklayers
Eight bricklayers build a house for 630 days. How many bricklayers must be added after 150 days to complete the building in (next) 320 days?
Correct answer:

Tips for related online calculators
Need help calculating sum, simplifying, or multiplying fractions? Try our fraction calculator.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
You need to know the following knowledge to solve this word math problem:
Related math problems and questions:
- Bricklayers
Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days?
- Complete 82405
8 masons build a house in 630 days. How many masons must we add after 150 days to complete the whole house in 320 days?
- Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days?
- Scientific notation mul
A student found the product of 8 × 10³ and 7 × 105 to be 5.6 × 108. What is the error? What is the correct product? Complete the explanation.
- Bricklayers
When a bricklayer works to redeem the house in 8 days, the other bricklayer will be finished in 10 days. How long will it take to make three such houses together?
- Revitalization 39191
Workers are building a new sidewalk while revitalizing the housing estate. Six workers will do the work in 12 days, but this is a problem because the sidewalk must be completed in 10 days to complete the work on time. How many workers must be hired to com
- Workers
Ten workers must pave the road for 22 working days. After four days were spent speeding up work, two more workers were added. a) After how many work days do workers complete the paved road? b) How many working days does a total paved road take?